USS HARPERS FERRY (LSD 49) FY25 SELECTED RESTRICTED AVAILABILITY

Recipient
NATIONAL STEEL AND SHIPBUILDING COMPANY
Awarding agency
Department of Defense
Sub-agency
Department of the Navy
Fiscal year
FY2025
Obligated (promised)
$94,586,730
Total obligation (detail)
$94,586,730
Potential value (ceiling)
$97,030,314
Outlaid (paid out, linked File C)
no linked financial data
Signed
Mar 28, 2025
Period of performance
Mar 28, 2025 – Oct 16, 2026
Competition
FULL AND OPEN COMPETITION
Offers received
2
Solicitation
NEGOTIATED PROPOSAL/QUOTE
Pricing
FIRM FIXED PRICE
NAICS
336611 — SHIP BUILDING AND REPAIRING
Award type
DEFINITIVE CONTRACT

Transactions (36)

0Mar 28, 2025$63,877,252USS HARPERS FERRY (LSD 49) FY25 SELECTED RESTRICTED AVAILABILITY
P00001Apr 28, 2025OTHER ADMINISTRATIVE ACTION$0USS HARPERS FERRY (LSD 49) FY25 SELECTED RESTRICTED AVAILABILITY
A00001May 19, 2025EXERCISE AN OPTION$167,737C430A, MODIFICATION TO EXERCISE OPTION ITEMS
A00002Jul 7, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$209,918C430A, MODIFICATION TO INCORPORATE GROWTH WORK AND ADDING MILESTONES
A00003Jul 17, 2025EXERCISE AN OPTION$1,383,955MODIFICATION TO EXERCISE POST-AWARD SUPPLEMENTAL PACKAGE AS NOTIONAL OPTION ITEM
A00004Jul 23, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$3,290,768C430A, MODIFICATION TO INCORPORATE GROWTH WORK.
A00005Jul 25, 2025EXERCISE AN OPTION$254,530CODE 430A, EXERCISE OPTION ITEM
A00006Aug 5, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE-$97,268CODE 430A, MODIFICATION TO DEOBLIGATE BASIC WORK AND INCORPORATE GROWTH WORK.
A00007Aug 20, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$243,214C430A, MODIFICATION TO FULLY FUND GROWTH WORK AND DE-OBLIGATE BASIC WORK.
A00008Sep 9, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$2,245,020C430A, MODIFICATION TO FULLY FUND NEW WORK, GROWTH WORK, AND DE-OBLIGATE BASIC WORK. UPDATE WAWF POC.
A00009Sep 18, 2025FUNDING ONLY ACTION$0C430A, MODIFICATION TO ADD MILSTRIP AND CORRECT LOA
A00010Sep 23, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$4,457,418C430A, MODIFICATION TO FULLY FUND NEW WORK AND GROWTH WORK.
A00011Oct 3, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE-$99,660C430A, MODIFICATION TO DE SCOPE AND FULLY FUND GROWTH WORK.
A00012Oct 9, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE-$142,847CODE 430A GROWTH AND DESCOPE RCCS
A00013Oct 17, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$46,672CODE 430A GROWTH AND DESCOPE RCCS
A00014Oct 20, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$394,763CODE 430A INCORPORATE GROWTH WORK
A00015Oct 21, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$457,480CODE 430A INCORPORATE GROWTH WORK
A00016Oct 30, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$77,821CODE 430A INCORPORATE GROWTH AND DESCOPE RCCS
A00017Nov 7, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$301,241CODE 430A: INCORPORATE GROWTH AND DESCOPE RCCS
A00018Nov 21, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$1,378,733CODE 430A: INCORPORATE GROWTH AND DESCOPE RRCS
A00019Dec 3, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE-$50,443CODE 430A: DESCOPE RCCS
A00020Dec 16, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$3,836,273CODE 430A: INCORPORATE GROWTH WORK DISCOVERED DURING AVAILABILITY
A00021Jan 6, 2026SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE-$61,766CODE 430A: DESCOPE RCCS
A00022Jan 21, 2026SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$2,029,542C430A: INCORPORATE GROWTH REQUIREMENT FOUND DURING AVAILABILITY
A00023Jan 30, 2026FUNDING ONLY ACTION$0C430A: ADMIN REALLOCATION
A00024Feb 4, 2026SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$3,815,963SWRMC CODE 430A USS MANCHESTER FY25 SRA MODIFICATION TO INCORPORATE ADDITIONAL WORK REQUIREMENTS AND TO DELETE WORK REQUIREMENTS
A00025Feb 27, 2026SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$1,834,189C430A USS HAPRERS FERRY MODIFICATION TO INCORPORATE ADDITIONAL WORK REQUIREMENTS AND TO DELETE WORK REQUIREMENTS
A00026Feb 27, 2026SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$667,420SWRMC C430A USS HARPERS FERRY CONTRACT MODIFICATION TO INCORPORATE ADDITIONAL WORK REQUIREMENTS AND TO DELETE WORK REQUIREMENTS
A00027Mar 12, 2026SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE-$106,603SWRMC C430A USS HARPERS FERRY CONTRACT MODIFICATION TO DESCOPE BASIC WORK REQUIREMENTS
A00028Mar 23, 2026SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$1,113,434SWRMC C430A USS HARPERS FERRY CONTRACT MODIFICATION TO INCORPORATE ADDITIONAL WORK AND DESCOPE BASIC WORK REQUIREMENT
A00029Mar 30, 2026CHANGE ORDER$493,091C430A, USS HARPERS FERRY (LSD 49) FY25 SRA, FULLY FUND AND OBLIGATE GROWTH WORK, UNILATERAL.
A00030Apr 2, 2026SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$1,439,655SWRMC C430A USS HARPERS FERRY CONTRACT MODIFICATION TO INCORPORATE ADD WORK AND DELETE WORK REQUIREMENT
A00031Apr 9, 2026CHANGE ORDER$63,406C430A, USS HARPERS FERRY (LSD 49) FY25 SRA, FULLY FUND AND OBLIGATE GROWTH WORK, UNILATERAL.
A00032Apr 21, 2026SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$124,805CODE 430A: USS HARPERS FERRY FY25 SRA DESCOPE AND GROWTH RCCS
A00033Apr 27, 2026SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$211,447SWRMC CODE 430A: USS HARPERS FERRY FY25 CONTRACT MODIFICATION TO REMOVE AND ADD WORK REQUIREMENTS
A00034Apr 28, 2026CHANGE ORDER$729,571SWRMC CODE 430A USS HARPERS FERRY FY25 SRA CONTRACT MODIFICATION TO UNILATERALLY ADD WORK REQUIREMENTS TO CONTRACT SCOPE