BORDER INFRASTRUCTURE-BARRIER GAPS DESIGN BUILD CONSTRUCTION

Recipient
GRANITE CONSTRUCTION COMPANY
Awarding agency
Department of Homeland Security
Sub-agency
U.S. Customs and Border Protection
Fiscal year
FY2025
Obligated (promised)
$193,687,547
Total obligation (detail)
$193,687,547
Potential value (ceiling)
$193,687,547
Outlaid (paid out, linked File C)
no linked financial data
Signed
Mar 14, 2025
Period of performance
Mar 14, 2025 – Nov 28, 2028
Competition
FULL AND OPEN COMPETITION
Offers received
5
Solicitation
SUBJECT TO MULTIPLE AWARD FAIR OPPORTUNITY
Pricing
FIRM FIXED PRICE
NAICS
236220 — COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION
Award type
DELIVERY ORDER

Transactions (9)

0Mar 14, 2025$70,285,846BORDER INFRASTRUCTURE-BARRIER GAPS DESIGN BUILD CONSTRUCTION
P00001Apr 30, 2025EXERCISE AN OPTION$23,071,624EXERCISES OPTIONAL LINE-ITEMS AWARDING THE DESIGN & CONSTRUCTION OF RIO GRANDE VALLEY-2 SEGMENT C-1 FOR NEW VERTICAL BARRIER, GAPS AND DRAINAGE AND EROSION CONTROL.
P00002May 13, 2025EXERCISE AN OPTION$1,611,155GRANITE RIO GRANDE VALLEY 2, 4, AND 10 BARRIER GAPS DESIGN BUILD CONSTRUCTION PROJECT MOD EXERCISING OPTIONAL LINE ITEMS 1007 THRU 1009 AND 1067 THROUGH 1069 ON THE PRICING SCHEDULE
P00003Jul 3, 2025EXERCISE AN OPTION$53,577,301DESIGN AND CONSTRUCTION OF NEW BARRIER WITHIN IN THE RIO GRANDE VALLEY, TX. THIS MOD EXERCISE OPTIONAL LINE ITEMS FOR DRAINAGE AND EROSION (COMPETED AT TIME OF AWARD).
P00004Sep 2, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$19,605,591EXERCISE OPTIONAL LINE ITEMS ADDING 1.4 MILES OF VERTICAL BORDER BARRIER IN THE RIO GRANDE VALLEY, TX.
P00005Sep 18, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$907,995ADD THE INSTALLATION OF A 36 INCH REINFORCED CONCRETE DRAINAGE PIPE AT THE EASTERN PORTION OF THE RGV 2 SEGMENT B-PROGRESSO PORT OF ENTRY.
P00006Feb 26, 2026OTHER ADMINISTRATIVE ACTION$0ADMINISTRATIVE MOD
P00007Mar 31, 2026SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$9,481,889ADD TIERED PRICING
P00008May 26, 2026SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$15,146,146ADDED CONSTRUCTION WORK

Record history in our archive

Outlay keeps a content-hashed copy of this record from every pull. No post-publication revisions observed so far.

  • detailfirst capture