THE WORK ASSOCIATED WITH THE HYRUM DAM SPILLWAY REPLACEMENT PROJECT WILL TAKE PLACE APPROXIMATELY 9 MILES SOUTHWEST OF LOGAN, UTAH IN CACHE COUNTY, UTAH. THE OVERALL WORK IS FOR THE CONSTRUCTION OF A NEW SPILLWAY AND THE REMOVAL OF THE EXISTING SPILL

Recipient
AMES FEDERAL CONTRACTING GROUP LLC
Awarding agency
Department of the Interior
Sub-agency
Bureau of Reclamation
Fiscal year
FY2025
Obligated (promised)
$115,012,088
Total obligation (detail)
$115,012,088
Potential value (ceiling)
$117,583,198
Outlaid (paid out, linked File C)
no linked financial data
Signed
Mar 21, 2025
Period of performance
Mar 21, 2025 – Feb 10, 2029
Competition
FULL AND OPEN COMPETITION
Offers received
5
Solicitation
NEGOTIATED PROPOSAL/QUOTE
Pricing
FIRM FIXED PRICE
NAICS
237990 — OTHER HEAVY AND CIVIL ENGINEERING CONSTRUCTION
Award type
DEFINITIVE CONTRACT

Transactions (11)

0Mar 21, 2025$112,100,000THE WORK ASSOCIATED WITH THE HYRUM DAM SPILLWAY REPLACEMENT PROJECT WILL TAKE PLACE APPROXIMATELY 9 MILES SOUTHWEST OF LOGAN, UTAH IN CACHE COUNTY, UTAH. THE OVERALL WORK IS FOR THE CONSTRUCTION OF A NEW SPILLWAY AND THE REMOVAL OF THE EXISTING SPILL
P00001Jun 10, 2025CHANGE ORDER$0THE PURPOSE OF THIS MODIFICATION IS TO DIRECT THE CONTRACTOR TO PERFORM ALL WORK NECESSARY TO REPAIR THE ACCESS ROAD THAT WAS DAMAGED BY WATER BURSTING FROM THE HYRUM FEEDER DITCH PIPE.
P00002Aug 19, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$0THE PURPOSE OF THIS MODIFICATION IS AS FOLLOWS: APPROVE THE MATERIAL SUBSTITUTIONS FOR THE HYRUM AND EAST FIELD CANAL SIPHONS, PROVIDE REVISED SECTIONS TO THE SPECIFICATIONS, AND PROVIDE REVISED DRAWING SECTIONS
P00003Sep 9, 2025SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$0THE PURPOSE OF THIS MODIFICATION IS TO UPDATE THE SPECIFICATIONS TO ALLOW FOR THE CAPPING OF PREVIOUSLY BURIED, NON-HAZARDOUS CONSTRUCTION MATERIAL THAT IS DISCOVERED DURING EXCAVATION OF THE DISTURBANCE AREA(S) DOCUMENTED IN THE ENVIRONMENTAL ASSESS
P00004Feb 10, 2026EXERCISE AN OPTION$1,228,890THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTIONAL LINE 3: SUPPLEMENTARY DEEP WELLS INSTALLATION/REMOVAL AND SUPPLEMENTARY DEEP WELLS MATERIALS, AND OPTIONAL LINE 4: SUPPLEMENTARY DEEP WELLS OPERATION AND POWER
P00005May 8, 2026SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$53,468THE PURPOSE OF THIS MODIFICATION IS TO ESTABLISH CONTRACT RATES FOR PROFIT, HOME OFFICE OVERHEAD, AND FIELD OFFICE OVERHEAD. ADDITIONALLY, THIS MODIFICATION INCLUDES AN ADJUSTMENT FOR THE DRILLING OF DEEP WELLS AND THE DEFINITIZATION OF UNDEFINITIZED
P00006May 19, 2026SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$66,040HYRUM DAM SPILLWAY REPLACEMENT
P00007May 19, 2026OTHER ADMINISTRATIVE ACTION$0HYRUM DAM SPILLWAY REPLACEMENT
P00008Jun 4, 2026SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$1,563,691THE PURPOSE OF THIS MODIFICATION IS TO ALLOCATE FUNDS FOR THE CONSTRUCTION OF A TEMPORARY ACCESS ROAD ON THE NORTH SIDE OF THE PROJECT IN ACCORDANCE WITH FAR 52.236-2 DIFFERING SITE CONDITIONS. THIS ACCESS IS NECESSARY FOR THE CONSTRUCTION OF THE STI
P00009Jul 14, 2026SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE$0THIS MODIFICATION INCORPORATES CLARIFICATIONS TO THE CONTRACT SPECIFICATIONS AND DRAWINGS. THE CLARIFICATIONS DO NOT CHANGE THE SCOPE OF WORK, CONTRACT PRICE, CONTRACT COMPLETION DATE, OR OTHER TERMS AND CONDITIONS OF THE CONTRACT.
P00010Jul 14, 2026OTHER ADMINISTRATIVE ACTION$0THE PURPOSE OF THIS MODIFICATION IS TO UPDATE THE START DATE OF CLIN 11. THIS IS AN ADMINISTRATIVE ACTION ONLY.